it is not a requirement. It has been common practice to paint, unpoured seals, yellow, and then red after pours, but it is not a requirement.Basically is there a red label requirement showing each seal off compound poured? Customer claims it's not code if not labeled.
I'm not quite sure what your comment intends.I would have never imagined gas could travel through a cable but that would only be required in a classified location. If the other end of the cable is installed in an unclassified location no seal is required.
This is interesting. Does anyone have photos? Do you paint the whole fitting? Or just a red / yellow ring around it? Is there a 'standard'?it is not a requirement. It has been common practice to paint, unpoured seals, yellow, and then red after pours, but it is not a requirement.
We just spray some green paint on the part of the fitting with the plug you screw back in after pouring the seal.This is interesting. Does anyone have photos? Do you paint the whole fitting? Or just a red / yellow ring around it? Is there a 'standard'?
...