Good morning, I'm working on a design that involved changing an aerial service to new underground service. I would like to ask for help on knowing a couple of thing on the new service entrance gear:

it is a 120/208v, 2000 amp MAIN DISCONNECT and meter, 65 KAIC service

1. while looking I'm not sure if this would be a free standing or wall mounted EZ-MAIN gear, any help?

2. Does it have to be EUSERC Type?

thanks
 