Greg1707
Senior Member
- Location
- Alexandria, VA
- Occupation
- Business owner Electrical contractor
I have a 200 amp residential service and need to replace the meter base. One of the connections on the load side is a problem. The current conductors on the load side as well as the line side will be too short once I install the new meter base.
The POCO conduit is steel. The house side conduit is PVC. If there were a way to lower the meter base one foot the existing conductors could be used.
If necessary I can replace the load side wires but what will POCO do about the too short line side?
This is a first for me. I have started a work order with Dominion Energy.
Does anyone have an idea of how this will go down?
The POCO conduit is steel. The house side conduit is PVC. If there were a way to lower the meter base one foot the existing conductors could be used.
If necessary I can replace the load side wires but what will POCO do about the too short line side?
This is a first for me. I have started a work order with Dominion Energy.
Does anyone have an idea of how this will go down?