360Youth
Senior Member
- Location
- Newport, NC
We were asked by a customer with an existing standby generator and 200 amp ATS feeding one panel of a 400 amp system if we could feed his second panel as well. Our proposal was to tap the generator conductors at the ATS and feed the second panel manually with an interlock kit so as not to overload the existing generator with additional loads. Assuming all load calculations, tap requirements, and installation methods are per NEC, is there anything prohibiting us from tapping the feeder conductors from the ATS at the first panel instead? It would be a shorter and cleaner run for the customer. My only caution is that the conductors on the interlock breaker would be energized all of the time as opposed to only when the generator is running, but the kit is still fulfilling its intended purpose. I would coordinate "phases" between as a precautionary should someone inadvertently over-ride the interlock down the road. Thanks.