Here`s the deal I wire a house drill a 2" hole under panel my cables come through up to panel.I also place a conduit in so after mechanical guy comes and places units I can access or pull my wires for these systems.I`m thinking 312.5c will stop this.But also where the cables come from under house to panel they are in a sense bundled for approx. 2 ft how do I know if I must derate for bundling?And could someone explain the process. Thanks