Just curious what method other electricians use when installing rigid steel outside between meter can and disconnect.I usually install myers hub to seal the enclosure. Is it acceptable to just use locknuts? or is this the standard practice.
are you installing side by side or one above the other? Side by side I use PVC and just use locknut and bushing-- I never installed one above the other.