We just had an inspector tell us that an installation was non-compliant because the 12/3 Romex ran for more than 10' in conduit. Essentially, we had to jump around an inaccessible portion of the crawl space so we stubbed out ran 20' of EMT then poked back into the crawl space. He cited 312.5(c) which I don't even think is a relevant code section. I think 344.15(B) not only allows it, but requires it.
I just want to make sure I am thinking about this correctly before I ask him to revisit this.