e57
Senior Member
- Location
- San Francisco, CA
Ever have one of those days when you realize you should have stayed at that summer job printing T-shirts and further studied art? This is the end of that day for me...
Spent nearly 2 days completing a 2" conduit run in footing at the last minute for a service conduit move, and change because the existing neutrals are rotten - surrounded by a frantic concrete crew, on a site that is a wall to wall tripping hazard hanging up-side down in forms and steel I get it done. I tell the concrete foreman exactly what I'm doing and he is right there next to me. The GC has been on the job in and out and spent time talking to me while I did this run. The Concrete contractor has also been in and out, knew where all this was running.... This morning as I am tidying up loose and and working on a separate conduit in another pour - he pulls this... "Ya know is there anywhere else you could go with that...." A: "Well not really at this point - it's done, and I have inspection at 1pm - but if you NEED me to move it, you need to tell me right now." So we talk about it and it basically comes down to the Building inspector, and the Engineer. (Who canc'ed out and won't be by until Wednesday - a job delay of 4 working days for the pour either way...) The building inspector comes by and says he can not find any code prohibiting where I ran the conduit, but leaves it up to the Engineer...
I talked to the Engineer for over a half-hour and sent pictures that we discussed over the phone. He too can not find any code or example of why or why I coundn't run it through there. (But at the word of the concrete contractor is hesitant to say yes or no...) He tells me he'll have to look into it some more, but regrets that he can't get out there himself to look at it... (I can hear dogs and children playing in the backround...)
So anyway time is ticking... And everyone who has been out to this job and seen what I was doing and completed one whole working day before, is now getting antsy, and for lack of better words - 'Accelerated'. Now it's "why would you even think of running through there in the first place!" (Who only an hour before was asking the concrete guy what his issue was with it...)
Time ticking away.... Near 1pm the 'accelerated' GC is having a fit in general and especially about me, and Electricians in general, and all our change orders - blah blah blah. 'And we caused the job this job delay, and he's gonna take it out of us..." I'm quick to remind him that the pour is delayed from the original already due to the Engineer not coming until Wendnesday.... And that he is yet to say anything difinative about my pipe work.
1:07 PM I'm waiting for the electrical inspector, and the Engineer calls, and repeats what he said about not being able to find any code, etc that would prohibit it, "But wants to see it in person on Wednesday before the pour on thursday morning to give a Yes or No because maybe there is an issue I can't see from here - even if it's not, maybe we can add some steel and make it OK."
I tell the GC and he flips! "You're gonna pay for this job delay" I walk away and cancel my inspection at 1:10, then up-date my employer about it - who has been caught in the middle just as much as I have been. He is already tweeked from the phone calls already, is upset that I pulled the plug on the inspection and begining to re-route out of this questionable area...
So at this point I have 3 days to re-do 2 days work, (which will probably only take 1.5 with the help I got from the Boss today) or risk of having the Engineer say 'no' on wednesday which would delay the pour until at least next friday... A delay of 1 day, on top of the 4 that the Engineer already caused - with a GC that will probably try to get you for all 5.
So outside of the Engineering aspect...
Spent nearly 2 days completing a 2" conduit run in footing at the last minute for a service conduit move, and change because the existing neutrals are rotten - surrounded by a frantic concrete crew, on a site that is a wall to wall tripping hazard hanging up-side down in forms and steel I get it done. I tell the concrete foreman exactly what I'm doing and he is right there next to me. The GC has been on the job in and out and spent time talking to me while I did this run. The Concrete contractor has also been in and out, knew where all this was running.... This morning as I am tidying up loose and and working on a separate conduit in another pour - he pulls this... "Ya know is there anywhere else you could go with that...." A: "Well not really at this point - it's done, and I have inspection at 1pm - but if you NEED me to move it, you need to tell me right now." So we talk about it and it basically comes down to the Building inspector, and the Engineer. (Who canc'ed out and won't be by until Wednesday - a job delay of 4 working days for the pour either way...) The building inspector comes by and says he can not find any code prohibiting where I ran the conduit, but leaves it up to the Engineer...
I talked to the Engineer for over a half-hour and sent pictures that we discussed over the phone. He too can not find any code or example of why or why I coundn't run it through there. (But at the word of the concrete contractor is hesitant to say yes or no...) He tells me he'll have to look into it some more, but regrets that he can't get out there himself to look at it... (I can hear dogs and children playing in the backround...)
So anyway time is ticking... And everyone who has been out to this job and seen what I was doing and completed one whole working day before, is now getting antsy, and for lack of better words - 'Accelerated'. Now it's "why would you even think of running through there in the first place!" (Who only an hour before was asking the concrete guy what his issue was with it...)
Time ticking away.... Near 1pm the 'accelerated' GC is having a fit in general and especially about me, and Electricians in general, and all our change orders - blah blah blah. 'And we caused the job this job delay, and he's gonna take it out of us..." I'm quick to remind him that the pour is delayed from the original already due to the Engineer not coming until Wendnesday.... And that he is yet to say anything difinative about my pipe work.
1:07 PM I'm waiting for the electrical inspector, and the Engineer calls, and repeats what he said about not being able to find any code, etc that would prohibit it, "But wants to see it in person on Wednesday before the pour on thursday morning to give a Yes or No because maybe there is an issue I can't see from here - even if it's not, maybe we can add some steel and make it OK."
I tell the GC and he flips! "You're gonna pay for this job delay" I walk away and cancel my inspection at 1:10, then up-date my employer about it - who has been caught in the middle just as much as I have been. He is already tweeked from the phone calls already, is upset that I pulled the plug on the inspection and begining to re-route out of this questionable area...
So at this point I have 3 days to re-do 2 days work, (which will probably only take 1.5 with the help I got from the Boss today) or risk of having the Engineer say 'no' on wednesday which would delay the pour until at least next friday... A delay of 1 day, on top of the 4 that the Engineer already caused - with a GC that will probably try to get you for all 5.
So outside of the Engineering aspect...
- Do you think I made the right call in deciding to re-route it?
Last edited: