Guys
If I want to run several conduits from 1st floor to second floor electrical rooms,
(3-4", 2-2", 3-1" all EMT) is it better to group all conduits and run them in same path,
then hit one spot at second electrical room floor slab?... or run them
from panel to panel individually?
If we have to core drill through beam when going from 1st floor through 2nd floor,
is there a max. conduit size allowed to go through beam? Thank you!
:slaphead:
If I want to run several conduits from 1st floor to second floor electrical rooms,
(3-4", 2-2", 3-1" all EMT) is it better to group all conduits and run them in same path,
then hit one spot at second electrical room floor slab?... or run them
from panel to panel individually?
If we have to core drill through beam when going from 1st floor through 2nd floor,
is there a max. conduit size allowed to go through beam? Thank you!
:slaphead: