bcm
Member
- Location
- Atlanta, Georgia
- Occupation
- Engineer
Hi friends!
I have a bit of a quandry with an inspector and an electrician about tapping service conductors and "safety".
There are existing 750 MCM service conductors in a trough. The design was to tap those 750 MCM conductors to add a new service point (meter/disconnect) for some cellular cabinets. The 750 MCMs are also tapped inside the trough to feed some other meters. At least one of the meters is fed by a set of 250 MCM. The electrician, instead of tapping the 750 MCM moved down the trough and tapped the 250 MCM before one of the meters and pulled #3/0s for the new meter. He claimed it was "safer" to do this than to tap the 750 MCM like everybody else did.
The local inspector isn't happy with what was done, but I haven't been able to get him to respond to me about why this is an issue.
I have my own instincts that say the electrician should be tapping somebody else's conductors for our client's meter, but I'm at a loss beyond that. So far, I haven't found anything helpful in the NE
Do you folks have any idea (outside of "it doesn't match the drawings") why the electrician would say tapping the 250MCMs are "safer" and why the inspector would be against doing this?
Thanks so much!
I have a bit of a quandry with an inspector and an electrician about tapping service conductors and "safety".
There are existing 750 MCM service conductors in a trough. The design was to tap those 750 MCM conductors to add a new service point (meter/disconnect) for some cellular cabinets. The 750 MCMs are also tapped inside the trough to feed some other meters. At least one of the meters is fed by a set of 250 MCM. The electrician, instead of tapping the 750 MCM moved down the trough and tapped the 250 MCM before one of the meters and pulled #3/0s for the new meter. He claimed it was "safer" to do this than to tap the 750 MCM like everybody else did.
The local inspector isn't happy with what was done, but I haven't been able to get him to respond to me about why this is an issue.
I have my own instincts that say the electrician should be tapping somebody else's conductors for our client's meter, but I'm at a loss beyond that. So far, I haven't found anything helpful in the NE
Do you folks have any idea (outside of "it doesn't match the drawings") why the electrician would say tapping the 250MCMs are "safer" and why the inspector would be against doing this?
Thanks so much!