This is my scanerio:
400 amp breaker feeds a machine center....uses 2 x 2" conduits with 3/0 wire (2 per phase, 3 phase)
We have to put in a safety switch that disconnects the mains.
We ran 4 x 2" conduits to the safety switch and are planning on pulling in 3 x 3/0 into each pipe.
My question is:
Do I need to run a 1/0 grounding/bonding conducter in each pipe?
Thanks for any help