jaylectricity
Senior Member
- Location
- Massachusetts
- Occupation
- licensed journeyman electrician
I have been working on a complete re-wire of a triple decker in South Boston for over a year. It was moving as fast as a herd of turtles. Lots of changes as the project went on and some money issues for the homeowner kept it from progressing nicely.
Finished the rough and passed inspection a few months ago. Unfortunately when the owner called for his insulation inspection the inspector shut the job down. Apparently the building permit he pulled was to gut the place, have new wiring, plumbing, insulation and sheetrock installed, but he had done a lot of framing to change the layouts of the apartments and add stairways for second egresses.
Anyway, it looks like instead of pulling a new permit, he's just going to sell the building and he has a serious buyer.
What happens to my permit? The permit was pulled on the 2005 code and one specific issue is the subpanels for each unit. When we purchased them they did not have 3 20 circuit panels and after comparing the prices we found that we could get away with 3 12/18 circuit panels using tandem breakers and still pay less than the larger panels. At the time there was only going to be 1-2 AFCI's for the bedrooms but if I have to re-pull the permit I'll be looking at 7-8 AFCI's, plus the 2-pole for the A/C unit. I imagine I'll have to replace the panels which leads me to the next question.
If I can talk to the new owner and be the one to finish the job will Inspectional Services be OK that all that work was actually done long before the new permit? And conversely, if the new owner doesn't want me to finish the job what does that do to my liability?
Finished the rough and passed inspection a few months ago. Unfortunately when the owner called for his insulation inspection the inspector shut the job down. Apparently the building permit he pulled was to gut the place, have new wiring, plumbing, insulation and sheetrock installed, but he had done a lot of framing to change the layouts of the apartments and add stairways for second egresses.
Anyway, it looks like instead of pulling a new permit, he's just going to sell the building and he has a serious buyer.
What happens to my permit? The permit was pulled on the 2005 code and one specific issue is the subpanels for each unit. When we purchased them they did not have 3 20 circuit panels and after comparing the prices we found that we could get away with 3 12/18 circuit panels using tandem breakers and still pay less than the larger panels. At the time there was only going to be 1-2 AFCI's for the bedrooms but if I have to re-pull the permit I'll be looking at 7-8 AFCI's, plus the 2-pole for the A/C unit. I imagine I'll have to replace the panels which leads me to the next question.
If I can talk to the new owner and be the one to finish the job will Inspectional Services be OK that all that work was actually done long before the new permit? And conversely, if the new owner doesn't want me to finish the job what does that do to my liability?