I need to set a panel down at my lake property, this is a non-code area. But lets do things right. The meter socket enclosure (80 ft away) also has a 100 amp breaker feeding the underground to this rain tight panel. The underground feeder will be done by the local power company.
The Code says to use Schedule 80 when subject to damage, (when running up to the box) which would be pretty hard to hit to do as this is set back near some trees. I'm thinking about Schedule 40 instead which If I were to bet 99.9% of the other work down there is done in. Comments??
The Code says to use Schedule 80 when subject to damage, (when running up to the box) which would be pretty hard to hit to do as this is set back near some trees. I'm thinking about Schedule 40 instead which If I were to bet 99.9% of the other work down there is done in. Comments??