SCR and load coupled Transformer Secondary Fuse Requirement

Status
Not open for further replies.

DustinPhillips

New member
Location
Richland, WA
The code requirement I'm looking at is NEC 450.3 (b) and 240.4(F) out of the 2017 NEC.

I am working on a furnace design that is being powered by a 3-phase 480 V supply and controlled by an SCR.

We are stepping down the voltage after the SCR to 45 V with a 480/45 delta-wye transformer.

SCR manufacturers don't recommend fusing downstream of the SCR because of potential equipment damage. Some manufacturers have examples with our same delta-wye setup that don't include secondary fusing.

240.4 (F) allows you to fuse the primary for secondary conductor protection in the case of a single-phase transformer having a 2 wire (single-voltage) secondary, or a three-phase, delta-delta connected transformer having a 3-wire (single-voltage) secondary.

I want to understand the reason why the code does not allow the same provision for a delta-wye.

This is also a system that would only be serviced by a "Qualified Person" and the transformer is only used for the furnace heater coils so I am also wanting to understand if this code requirement applies to systems like the one described above.
 
Status
Not open for further replies.
Top