I'm inspecting electrical/instrumentation on eight crude oil truck unloading stations (Class 1, Div 2 areas). Station skids are all supplied with seal offs, properly installed. Commissioning is complete for two skids that are the first to be used in unloading product. Seals are not poured but owner is proceeding with unloading of 50 tanker trucks claiming it is part of the commissioning process. Is this in violation of Federal Regs? If so, which one(s)? I'm not certain where to begin in looking at CFRs.