Situation:
480-208/120V 500kVA step down, located outdoors
primary OCP: 600A
Secondaries tap to two distribution panels inside a building. Panels are mounted such that the conductors will stub into the panels after penetrating through the building.
Regardless if it is one or two secondary taps, should secondary protection be supplied outside at the transformer, or is the MCB at the panel sufficient? My understanding that because it outside, tap rule secondary tap rule would not apply and the OCP should be at the nearest point of entry.
480-208/120V 500kVA step down, located outdoors
primary OCP: 600A
Secondaries tap to two distribution panels inside a building. Panels are mounted such that the conductors will stub into the panels after penetrating through the building.
Regardless if it is one or two secondary taps, should secondary protection be supplied outside at the transformer, or is the MCB at the panel sufficient? My understanding that because it outside, tap rule secondary tap rule would not apply and the OCP should be at the nearest point of entry.