2005 NEC. 700.27 states that "Emergency system(s) overcurrent devices be selectively coordinated". Figure 517.30 No.1 sketch shows the equipment system as part of the "Essential Electrical System" but outside of the Emergency electrical system.
Is the HVAC equipment system required to be part of Selective Coordination?
Is the HVAC equipment system required to be part of Selective Coordination?