When considering selective coordination compliance for emergency systems, do you find it necessary and/or typical for the engineering to figure the time-current curves to be coordinated all the ay into the instantaneous range (<100 mSec/6 cycles) or is the short time and long time domains sufficient.
There is some conflict between the NEC and NFPA 110 on this issue. The Florida Agency for Healthcare Administration (AHCA) standards appear to NOT consider the instantaneous region.
Any thoughts on this?
There is some conflict between the NEC and NFPA 110 on this issue. The Florida Agency for Healthcare Administration (AHCA) standards appear to NOT consider the instantaneous region.