chiefkona1145
Member
I have a question regarding a new generator being added to an existing building distribution system. The new generator is at the exterior of the building and the feeds from it go underground into the building to a new 4 pole automatic transfer switch; the normal side of the transfer switch is from a transformer connected downstream from the building service. Does this generator need a #3/0 (or #4/0) ground conductor that is bonded to the transfer switch and transformer? The feeds from the generator are parallel (4) sets of 4-1/C 500 KCMIL and each conduit includes a #3/0 ground conductor.
Any help with this including a code reference would be greatly appreciated.
Thanks
Any help with this including a code reference would be greatly appreciated.
Thanks