Good morning all,

Does anyone know how long it takes for the commissioning agent to generate the script for the SOO for the Main Switchgear? I am curious to know what programming they use.

Any response is much appreciated.

Thanks,
 
You need to provide a lot more details about your installation.

I have done some scripts in as little as 1 hour and others that took 6 months to get approval.
 
You need to provide a lot more details about your installation.

I have done some scripts in as little as 1 hour and others that took 6 months to get approval.

Thanks, Jim.

It is a 3000A Switchgear with a Bus duct rated to 4000A. It has a backup Generator to start up within 5 secs of the power outage. Good to know about the timelines on the scripts.
 