lhenk
New member
- Location
- Harrisburg, IL
I have a house with an existing overhead service attached to the side of the house with the weatherhead under the eaves. It is a 100 amp service that has been in place for many years, perhaps as far back as the 1970's.
I got a letter in the mail from the utility company telling me that during a recent inspection they discovered a NESC clearance issue and that I would have to correct it or have my power turned off.
I can see from their 2014 overhead electric installation drawings that they require 12" clearance above the weatherhead to the eaves. If I had modified this service or newly installed it then I agree that I should meet these current requirements. However, since this service has been in place and untouched for many years I don't see how I can be expected to change it now. If the service did not meet their requirements at the time it was installed they never would have started service to begin with, therefore it must have met their requirements at the time.
I have found 3 other utility companies in the Midwest that have their clearance requirements online and none of those 3 require the minimum 12" clearance that my utility company requires. Since these other 3 companies don't require the same 12" clearance then I think this may be a local utility company requirement and not an NESC clearance requirement.
Can anyone tell me if this is a long standing NESC requirement?
I got a letter in the mail from the utility company telling me that during a recent inspection they discovered a NESC clearance issue and that I would have to correct it or have my power turned off.
I can see from their 2014 overhead electric installation drawings that they require 12" clearance above the weatherhead to the eaves. If I had modified this service or newly installed it then I agree that I should meet these current requirements. However, since this service has been in place and untouched for many years I don't see how I can be expected to change it now. If the service did not meet their requirements at the time it was installed they never would have started service to begin with, therefore it must have met their requirements at the time.
I have found 3 other utility companies in the Midwest that have their clearance requirements online and none of those 3 require the minimum 12" clearance that my utility company requires. Since these other 3 companies don't require the same 12" clearance then I think this may be a local utility company requirement and not an NESC clearance requirement.
Can anyone tell me if this is a long standing NESC requirement?