I'm currently building a 900 square foot commercial building. The original prints had my meter and building disconnect in the electrical room with my distribution panel and 2 sub panels. Now, they want a meter pedestal with the service disconnect 180 feet away from the distribution panel, outside the building.
My question is if this complies with 230.70(A)(1) as readily accessible or do I need a local disconnect in the electrical room? The 400 amp service from the meter pedestal would otherwise land directly on lugs with 2 sub feed breakers for my sub panels.