Are there any requirements in the NEC which dictate how conduit for 480V SE conductors need to be installed (ductbank vs buried conduit)?
I assume that this would be dependent on how conduit was routed (under roadways, etc...) but just looking at the simple case where there is a utility padmount transformer directly outside of a building with SE conductors routed to SE equipment inside of building are there any requirements specific to conduit installation?
For the above I'm assuming that the utility metering point is at service transformer with customer then owning service entrance conductors. Does the answer change if the utility metering are in SE equipment (Switchboard, etc...) in which case I believe the utility would then own those conductors?
I'm looking at a few projects that would involve intercepting existing SE conductors and in the process of trying to anticipate what to expect (no good drawings) wondered if there was a conduit installation requirement that typically governed such installations?
Thanks
I assume that this would be dependent on how conduit was routed (under roadways, etc...) but just looking at the simple case where there is a utility padmount transformer directly outside of a building with SE conductors routed to SE equipment inside of building are there any requirements specific to conduit installation?
For the above I'm assuming that the utility metering point is at service transformer with customer then owning service entrance conductors. Does the answer change if the utility metering are in SE equipment (Switchboard, etc...) in which case I believe the utility would then own those conductors?
I'm looking at a few projects that would involve intercepting existing SE conductors and in the process of trying to anticipate what to expect (no good drawings) wondered if there was a conduit installation requirement that typically governed such installations?
Thanks