I failed an inspection today. Unfortunately, the general contractor scheduled all the inspections and I was not present to defend myself.
I replaced a main panel as well as did a lot of electrical work involving a kitchen remodel.
The service equipment outside has a meter and a 150 amp breaker disconnect. The panel inside is fed by a four wire feeder. The inspector failed me because my permit was for a sub panel and not a "service change." There is an additional fee for service changes. I also failed because I did not have a wire connecting the panel to the cold water pipe.
I need to call him tomorrow and am not sure how to approach this. I feel he is wrong.
Any suggestions?
I replaced a main panel as well as did a lot of electrical work involving a kitchen remodel.
The service equipment outside has a meter and a 150 amp breaker disconnect. The panel inside is fed by a four wire feeder. The inspector failed me because my permit was for a sub panel and not a "service change." There is an additional fee for service changes. I also failed because I did not have a wire connecting the panel to the cold water pipe.
I need to call him tomorrow and am not sure how to approach this. I feel he is wrong.
Any suggestions?