I have a customer that has bought a Wire Rope shop and it has a 480v 3ph 200A service. It has a 25KVA 480v primary an 120/240 Delta secondary for another Panel. The customer has all 120/240V 3ph equipment to use.
75A Press
45A press
30A wire spooling machine
17A Test bed
Instead of using transformer to accommodate this would it make more sense to just redo Service to a 120/240 3Ph Service like a 400A
75A Press
45A press
30A wire spooling machine
17A Test bed
Instead of using transformer to accommodate this would it make more sense to just redo Service to a 120/240 3Ph Service like a 400A