Sewage ejector pump on a project installed outside the building. The building is slab on grade, no basement.
Would you consider the pump a 700, 701 or 702 load? Obviously if it is 702, then the client could choose not to have backup power at all if they choose.
I would consider it 702, but I'm being told that there is some type of EPA regulation identifying it as a 700 or 701.
Anyone deal with this before?