I was asked to review a project, an existing small private sewage treatment plant that is to be supplied with a dedicated electrical service, rather than be sub fed from an existing facility.
Existing facilities:
Small, private sewage treatment plant serving two buildings on a common site.
Pole building is served via a residential 200 amp load center located in a small room within the main pole building.
2 underground wet wells, with exterior control panel being fed with PVC, and GRS serving the pumps, and floats below in the tank, and (no sealoffs) in GRS pipe.
Sewage treat tanks (open to atmosphere) in pole barn with PVC conduit serving the sensors, floats, motors, etc.
The pole barn interior wiring is all romex wiring, metal and plastic boxes, with standard interior devices.
It is no problem to provide a dedicated service for this building
BUT
With the information that I have outlined above, I feel the existing circuiting does not meet code (no classified circuiting), and that if a new service was to be installed, the installing party would be liable for connecting the existing non code compliant to the new service.
Am I correct about the existing branch circuiting needing to be in a classified raceway system ?
Thanks
Tom
Existing facilities:
Small, private sewage treatment plant serving two buildings on a common site.
Pole building is served via a residential 200 amp load center located in a small room within the main pole building.
2 underground wet wells, with exterior control panel being fed with PVC, and GRS serving the pumps, and floats below in the tank, and (no sealoffs) in GRS pipe.
Sewage treat tanks (open to atmosphere) in pole barn with PVC conduit serving the sensors, floats, motors, etc.
The pole barn interior wiring is all romex wiring, metal and plastic boxes, with standard interior devices.
It is no problem to provide a dedicated service for this building
BUT
With the information that I have outlined above, I feel the existing circuiting does not meet code (no classified circuiting), and that if a new service was to be installed, the installing party would be liable for connecting the existing non code compliant to the new service.
Am I correct about the existing branch circuiting needing to be in a classified raceway system ?
Thanks
Tom