ivsenroute
Senior Member
- Location
- Florida
I am doing some private work for a bank inspecting an extremely large residential home as it is constructed. It is a massive project, all concrete, including 18" of concrete between floors. Rather unique and quite the bunker.
Anyway, I stopped in and was taking some photos of the 400A main panel and I noticed that they had a #6 bare copper coming out of the panel & went through the foundation to the exterior.
They already have a 1/0 bare copper wire running through the entire footer all the way around this complex and it is attached at 6 of the corners with 8' ground rods so the GEC system is extensive and oversized.
I asked the guys what the bare copper wire was going out to bond and they said that it went outside to the 2 ground rods that they had to add. I asked why they had to add them. The answer was that the inspector said they were required and told them what to do.
I just shook my head, what a waste.
Anyway, I stopped in and was taking some photos of the 400A main panel and I noticed that they had a #6 bare copper coming out of the panel & went through the foundation to the exterior.
They already have a 1/0 bare copper wire running through the entire footer all the way around this complex and it is attached at 6 of the corners with 8' ground rods so the GEC system is extensive and oversized.
I asked the guys what the bare copper wire was going out to bond and they said that it went outside to the 2 ground rods that they had to add. I asked why they had to add them. The answer was that the inspector said they were required and told them what to do.
I just shook my head, what a waste.