We replaced one existing electrical panel -225A, 208/120V, 3PH with a new panel at very much same location, re-use existing conduit but pull new wires. We went to site and did not find where its source panel as all existing conduit ran above ceiling, we had note on drawing for EC to verify its source panel later in construction. The replaced panel does not have manufacture name tag, we guess it is 10 kAIC... We noted new panel to be 22KAIC on print to be safe.
The plan inspector fails the project and ask for the short circuit calculation per NEC 2020 408.6 for the new panel, we can do the estimate SC to satisfy him but have no clue where the source is because the building is so old, main elec. room is 300 feet plus away from panel location. BTW, it takes us 5 hours driving to site from out office. What can we do under this situation to satisfy the inspector and still comply with code? Are there any exemptions in codes? One thought is power the new panel from existing main elec. room which we knew all the sources and can calculate the SC, but it will cost more because of long run... I am an elec. designer.
The plan inspector fails the project and ask for the short circuit calculation per NEC 2020 408.6 for the new panel, we can do the estimate SC to satisfy him but have no clue where the source is because the building is so old, main elec. room is 300 feet plus away from panel location. BTW, it takes us 5 hours driving to site from out office. What can we do under this situation to satisfy the inspector and still comply with code? Are there any exemptions in codes? One thought is power the new panel from existing main elec. room which we knew all the sources and can calculate the SC, but it will cost more because of long run... I am an elec. designer.