We are working on a C&I rooftop solar project and are looking for suggestions on shunt trip for our main breaker. We have a customer owned transformer that is a Delta:Wye configuration, with Delta on the utility side at 13.2 kV and Wye on the customer side at 480V. Utility got back to us and requested that we add a shunt trip in the main breaker to detect any phase loss on the primary, Delta side of the transformer.
We understand their concern and we are looking at options. We are running into issues as the phase loss detection has to happen on the 13.2 kV side. Has anyone come across similar situation and does anyone have any recommendation? For anyone who is curious, this will be a 750 kW DC/480 kW AC system with 4 x SolarEdge 120s.
We understand their concern and we are looking at options. We are running into issues as the phase loss detection has to happen on the 13.2 kV side. Has anyone come across similar situation and does anyone have any recommendation? For anyone who is curious, this will be a 750 kW DC/480 kW AC system with 4 x SolarEdge 120s.