RichB
Senior Member
- Location
- Tacoma, Wa
- Occupation
- Electrician/Electrical Inspector
Hi all,
Looked thru the archives and google and just can't find an answer to a simple question(s)-
If therre is a change to the load side does that affect the calcs and if so--How big of a change is needed?
Example--If we were to require and arc flash analysis to be included as part of the contract documents--then there is a future (couple years later) load change of 20 amps to an existing 50 amp load, for a total of 70 amps--will this require a recalculation --or what would trigger a recalc for a load side addition?
Or--am I over thinking this?:happysad::?
Thanks all
RichB
Looked thru the archives and google and just can't find an answer to a simple question(s)-
If therre is a change to the load side does that affect the calcs and if so--How big of a change is needed?
Example--If we were to require and arc flash analysis to be included as part of the contract documents--then there is a future (couple years later) load change of 20 amps to an existing 50 amp load, for a total of 70 amps--will this require a recalculation --or what would trigger a recalc for a load side addition?
Or--am I over thinking this?:happysad::?
Thanks all
RichB
Last edited: