MFS-PDX-313
Member
- Location
- Tualatin, Oregon, USA
- Occupation
- Electrical design engineer, Industrial equipment
Designing a system for a customer. They're supplying 208 three-phase wye. Which is great since the pumps we use run on that. They also want us to use two heaters. The heaters are 208 single-phase, so they get wired leg to leg. My question is, do I use a two-pole breaker to feed each heater? I was already planning on using a single-pole SSR to control the heater, but that's different.