excited_electrone
Member
- Location
- Canada
- Occupation
- Electrical E.I.T
Hello all,
I am estimating a transformer for a package of 3 motors, it's a hydraulic unit, two 250Hp & one 60Hp, rated at 460V. Incoming line is 4160V. The application is a hoist operation.
Now, referring to table 44, C22.1-18, current ratings for three phase ac motors, I have got total load of 302A*2+77A*1 = 681A at 460V. So, calculating kVA demand for this load is = 681*1.732*460 = 542,566 VA. Now, allowing 1.5 multiplication factor for the hoist operation, I was told by seniors that hoist operations are different than normal cases so we use 1.5-1.7 multiplication factor for estimating, I come to 814kVA. And I sized transformer for 750kVA, which might get changed!
So, my question is what about the inrush current? What things I have to take into consideration while sizing a transformer with inrush current available?
Thank you!
I am estimating a transformer for a package of 3 motors, it's a hydraulic unit, two 250Hp & one 60Hp, rated at 460V. Incoming line is 4160V. The application is a hoist operation.
Now, referring to table 44, C22.1-18, current ratings for three phase ac motors, I have got total load of 302A*2+77A*1 = 681A at 460V. So, calculating kVA demand for this load is = 681*1.732*460 = 542,566 VA. Now, allowing 1.5 multiplication factor for the hoist operation, I was told by seniors that hoist operations are different than normal cases so we use 1.5-1.7 multiplication factor for estimating, I come to 814kVA. And I sized transformer for 750kVA, which might get changed!
So, my question is what about the inrush current? What things I have to take into consideration while sizing a transformer with inrush current available?
Thank you!