EBSoares
Member
- Location
- McKinney, TX
- Occupation
- Electrical Engineer
Hi, all.
Certain receptacles on non-dwelling kitchen (say, a fire department, for example) are clearly dedicated, such as refrigerators, garbage disposals, certain microwaves (if the receptacle is behind its embedded cabinet location), and so far we understand the panel load calculations have to abide by NEC 220.14(A).
However, for the general receptacles above the kitchen counters (say, there are (5) such receptacles throughout the kitchen), the architect is saying that (2) receptacles should be dedicated for their (2) coffee pots.
Question: Regarding panel schedule load calculation, for those two receptacles, do we calculate them as their full appliance load at around 1000VA each (as detailed by the NEC article in question), or do we treat each of those two like the others "unassigned" receptacles with loads of only 180VA?
I've come across two answers to this:

Certain receptacles on non-dwelling kitchen (say, a fire department, for example) are clearly dedicated, such as refrigerators, garbage disposals, certain microwaves (if the receptacle is behind its embedded cabinet location), and so far we understand the panel load calculations have to abide by NEC 220.14(A).
However, for the general receptacles above the kitchen counters (say, there are (5) such receptacles throughout the kitchen), the architect is saying that (2) receptacles should be dedicated for their (2) coffee pots.
Question: Regarding panel schedule load calculation, for those two receptacles, do we calculate them as their full appliance load at around 1000VA each (as detailed by the NEC article in question), or do we treat each of those two like the others "unassigned" receptacles with loads of only 180VA?
I've come across two answers to this:
- Abide by NEC 220.14(A). Since we know those two appliances that will be placed on the counter, we have to assign their full, 1000VA load to those (2) receptacles on the panel schedule.
- Disregard NEC 220.14(A). Since their locations and usage are not hard-set (the tenants can later move the coffee pots to other, generic receptacles on that counter, or end up buying just one coffee pot, or many other scenarios that don't match the design), all those (5) above-counter receptacles should simply be assigned 180VA each.
