tspisak
Member
- Location
- Corning, NY
I have a 60ft "portable" conveyor (on casters) with a motor starter panel located in the center - off each end are smaller conveyors on casters. My question: Can SO cord be used for the 480 vac power to each of the motors with twist lock plugs between sections?
I would rather go with the safer solution of running conduit (maybe liquidtite) to each end of the 60ft conveyor and then jumper between the conveyors with short SO cables. This would satisfy the "protection from damage" part of the code.
The code book is a little vague since this conveyor is "portable" and not building structure. What would be your solution if the 60ft conveyor was bolted to the floor?
I would rather go with the safer solution of running conduit (maybe liquidtite) to each end of the 60ft conveyor and then jumper between the conveyors with short SO cables. This would satisfy the "protection from damage" part of the code.
The code book is a little vague since this conveyor is "portable" and not building structure. What would be your solution if the 60ft conveyor was bolted to the floor?