scrumi
Member
- Location
- Walla Walla, WA
I have a customer that would like to be able to switch his solar production between two seperate electrical services from the same utility. The first service is the residential rate schedule and the second is the irrigation rate schedule.
It is somewhat unique as the irrigation service is a 3 phase high leg delta I did get permission from the utility to backfeed two of the three legs because of the configuration and I don't have to phase balance. So I can use single phase inverters to connect to either service.
there will be 22.5kW of solar production at peak and my plan was to run it into a manual transfer switch so they can just switch production between services.
The local inspector is a little confused about this and isn't sure it is possible I'd like to be able to point him the right direction.
It is somewhat unique as the irrigation service is a 3 phase high leg delta I did get permission from the utility to backfeed two of the three legs because of the configuration and I don't have to phase balance. So I can use single phase inverters to connect to either service.
there will be 22.5kW of solar production at peak and my plan was to run it into a manual transfer switch so they can just switch production between services.
The local inspector is a little confused about this and isn't sure it is possible I'd like to be able to point him the right direction.