Looking to see how this is typically interpreted within the industry.
If you have a spec that you have to have a % spare conduit, how do you calculate that percentage? Spare / Used ? Spare / (Spare + Used)? etc?
Let's say the requirement is 25% spare, and you'll be using 4 parallel conduits in this run. Do you need 1 spare conduit or 2 in order to get to 25%?
(1/4 = 25%)
(1/5 = 20%)
(2/5 = 40%)
If you have a spec that you have to have a % spare conduit, how do you calculate that percentage? Spare / Used ? Spare / (Spare + Used)? etc?
Let's say the requirement is 25% spare, and you'll be using 4 parallel conduits in this run. Do you need 1 spare conduit or 2 in order to get to 25%?
(1/4 = 25%)
(1/5 = 20%)
(2/5 = 40%)