N nivekbro Member Location Florida Occupation Electrician Tuesday at 7:18 PM #1 Good night Mike Holt when comes to SPD requirement. If you have a 320 continuous meter with double lugs feeding two separate mains how many SPD are required to be installed.
Good night Mike Holt when comes to SPD requirement. If you have a 320 continuous meter with double lugs feeding two separate mains how many SPD are required to be installed.
infinity Moderator Staff member Location New Jersey Occupation Journeyman Electrician Tuesday at 7:32 PM #2 What code cycle?
N nivekbro Member Location Florida Occupation Electrician Tuesday at 7:49 PM #3 2024 but down here in south Florida we just start to use 2020 code cycle