Keri_WW
Senior Member
Question: For a type 2 SPD that is protecting a switchboard, does it matter where in the lineup it is installed?
Details: I have had to take over a project in construction for an engineer that has left the company. He rejected the first switchboard submittal stating that the SPD needed to be in breaker position 1. The manufacturer says this is not possible since the bussing is offset for bigger breakers first. I don't think it matters where the SPD is installed, but wanted to see if there was a legitimate reason for location.
Thanks,
Keri
Details: I have had to take over a project in construction for an engineer that has left the company. He rejected the first switchboard submittal stating that the SPD needed to be in breaker position 1. The manufacturer says this is not possible since the bussing is offset for bigger breakers first. I don't think it matters where the SPD is installed, but wanted to see if there was a legitimate reason for location.
Thanks,
Keri