wireperson
Senior Member
- Location
- Florida
I got a set of drawings to bid in a commercial job , this is my first time bidding a commercial new construction, while doing a take off ,the drawings call for some fixtures but it doesn't specify make or model ,for instance it says Awning lights or security wall pack 250 w MH , then 8' fluorescent fistures, also the lay-ins 2x4 doesn't say how many lamps 2,3,or 4.Anoher that realised was that I have 2 sub panels that the schedule says that they are 3 phase but the breaker for them are 2 pole breakers (single phase) , also thhe load calculation is wrong this is a 120/208 job and he is using 360va in the load calc.
what should I do in this case? should I ask the GC? or architec for more info or specifications? shoud I make my bid with fixtures of my preference?
what should I do in this case? should I ask the GC? or architec for more info or specifications? shoud I make my bid with fixtures of my preference?