We are installing a 200kva ups unit. We are transferring 3 ckts from the existing gear and feeding it off of the ups. Our downtime is extremely limited due to the nature of the loads. My original plan was to splice the new conductors from the ups with the existing conductors located in the switch gear.
My boss brought up 408.3(3). Are there any exceptions to this section? The alternative is to install a junction box above the gear and remove the existing feeders and splice in the box, however, this will increase the downtime significantly. Any ideas are greatly appreciated.