Quick question that was brought up in a meeting yesterday.
We have an 800 foot run from a sub panel to feed a LV lighting transformer for small led lights.
We have 3 pull points along the way. Someone suggested why not run #10 to the first one #8 from 2nd to third and #6 from 3rd to end of run.
The plan is to pull #6 all the way. I’ve always pulled the same size wire from end to end with a small piece of smaller wire at the very end. However, I know just because “I’ve always done it this way!” Doesn’t make it correct...
So would this proposed way be acceptable? Why or why not.
Also. I am just generalizing the lengths and sizes. Just for a theoretical question we’re assuming the wire size is rated for the load to be delivered at each pull point.
Thanks!
We have an 800 foot run from a sub panel to feed a LV lighting transformer for small led lights.
We have 3 pull points along the way. Someone suggested why not run #10 to the first one #8 from 2nd to third and #6 from 3rd to end of run.
The plan is to pull #6 all the way. I’ve always pulled the same size wire from end to end with a small piece of smaller wire at the very end. However, I know just because “I’ve always done it this way!” Doesn’t make it correct...
So would this proposed way be acceptable? Why or why not.
Also. I am just generalizing the lengths and sizes. Just for a theoretical question we’re assuming the wire size is rated for the load to be delivered at each pull point.
Thanks!