I Have A Question About Splicing In A Condulet And The Size Of Condulet Required. I Have An Electrical Contractor That Has Installed A "T" Condulet (12.50 CU In) And Has Pulled (3) #6 THHN Phase Conductors & (3) #10 THHN Phase Conductors With A #10 THHN Equipment Ground Conductor. THe #10 Equipment Ground Has Been Spliced In The Condulet And Then Run To Each Piece Of Equipment. My Question Deals With 1999 NEC 370-16(c) And Table 370-16(b).
The Way I Read It Is If You Pull Straight Through The Condulet Then You Use The Information In Table 1 Of Chapter 9 For Conduit Fill. But If You Make A Splice You Need To Use Table 370-16(b). If This IS Correct How Do You Use This Table?
{ie 3-#6 Equals 15.0 Cu IN So I am Over The 12.5 Cu In Capacity And Therefore It Is Not Allowed}
Thanks For Any Help On THis Matter.
Ed
The Way I Read It Is If You Pull Straight Through The Condulet Then You Use The Information In Table 1 Of Chapter 9 For Conduit Fill. But If You Make A Splice You Need To Use Table 370-16(b). If This IS Correct How Do You Use This Table?
{ie 3-#6 Equals 15.0 Cu IN So I am Over The 12.5 Cu In Capacity And Therefore It Is Not Allowed}
Thanks For Any Help On THis Matter.
Ed