SamsTLC
Member
- Location
- Ocean county, NJ
- Occupation
- Electrical Contractor
I am wiring an extension to a school building. The Front portion of the building, which had the original MDP has been demolished to make place for a new larger two-story structure. I am installing a new MDP that will be about 20' away from where the original MDP was.
The entire facility is slab on grade. When the GC demolished the original slab and when we removed the old MDP, all underground feeder conduits had to be cut. Also, as they were digging for footings some more conductors were broken and cut.
My question is this: Is there a legal way to splice conductors running through conduit below grade without leaving access?
repairing the conduit and refeeding new conductors would not be cost-effective since some of the feeders are over 400' long, while I need to extend these wires 50' at most.
The entire facility is slab on grade. When the GC demolished the original slab and when we removed the old MDP, all underground feeder conduits had to be cut. Also, as they were digging for footings some more conductors were broken and cut.
My question is this: Is there a legal way to splice conductors running through conduit below grade without leaving access?
repairing the conduit and refeeding new conductors would not be cost-effective since some of the feeders are over 400' long, while I need to extend these wires 50' at most.