I have a project for 2670 sq ft.
106 single gang box, 9 two gang box, 1 three gang box, 10-3-1/2 side nail, 10-3-1/2 bar hanger, 13- 4-0 pancake, 12 Fan box, 61 duplex receptacle, 9 gfci receptacle, 1 range receptacle, 1 dryer receptacle, 6 telephone plate, 9 cable jack plate, 9 smoke detector, 1 chime kit, 20 single pole switch, 6 three way switch, 3 single pole dimmers, 2 three way dimmer and 3 occupancy sensor switch, 2 exhaust fan 80 CFM panasonic, disposal, dishwasher, range, micro/hood, refrigerator, 2 furnace, tv & telephone wire. NOT INCLUDED is 200 A meter center & a 125 A load center, AC System. Also my question if you can answer is? Do contractors normarly charge appliance circuirts in the kitchen or is the SQ FT price is included in the proposal or do they charge for each appliance circuit for example: disposal, dishwasher, micro/hood, range, dryer, refrigerator
 

satcom

Senior Member
Do contractors normarly charge appliance circuirts in the kitchen or is the SQ FT price is included in the proposal or do they charge for each appliance circuit for example: disposal, dishwasher, micro/hood, range, dryer, refrigerator

Neither way, EC's that have been in business for a while know there is no such thing as square foot pricing, the jobs are estimated and every assembly unit is priced up and marked up then totaled up for a project price, one botton line contract price.
Have you ever seen a square foot of nm cable, or a square foot switch box? It sounds like the builder is trying to telling you what to do
 

480sparky

Senior Member
Location
Iowegia
Any resi job that specifically lists a bunch of stuff like dimmers, occpuancy sensors and the like are not spec jobs. They are customs, and customs just cannot be bid by the ft?.
 

480sparky

Senior Member
Location
Iowegia
so your saying individual circuits are additional cost?

The stuff I highlighted in red are not required by the NEC: (Smokes are not highlighted as they are most likely required by local building/fire codes, same with bath fans)

I have a project for 2670 sq ft.
106 single gang box, 9 two gang box, 1 three gang box, 10-3-1/2 side nail, 10-3-1/2 bar hanger, 13- 4-0 pancake, 12 Fan box, 61 duplex receptacle, 9 gfci receptacle, 1 range receptacle, 1 dryer receptacle, 6 telephone plate, 9 cable jack plate, 9 smoke detector, 1 chime kit, 20 single pole switch, 6 three way switch, 3 single pole dimmers, 2 three way dimmer and 3 occupancy sensor switch, 2 exhaust fan 80 CFM panasonic, disposal, dishwasher, range, micro/hood, refrigerator, 2 furnace, tv & telephone wire. NOT INCLUDED is 200 A meter center & a 125 A load center, AC System. Also my question if you can answer is? Do contractors normarly charge appliance circuirts in the kitchen or is the SQ FT price is included in the proposal or do they charge for each appliance circuit for example: disposal, dishwasher, micro/hood, range, dryer, refrigerator
 
Status
Not open for further replies.