Hello everyone,
I've been tasked with a matter to determine if someone violated any NEC standards or at least standard practice within our field. To keep this simple and brief, an electrician was called for a furnace not working. It was determined the wiring in the conduit above the furnace supplying it shorted out due to a crack in the furnace allowing significant heat to escape and attack the conduit above. The wires were pulled out and replaced. Days later, same issue; wires again pulled out and replaced. Third time, within the same week, electrician replaces conduit and wire because wire was welded to the conduit inside. Fourth time the place burns down with witnesses reporting seeing and hearing significant arcing in the area of the conduit above the furnace and then a fire started in that area.
My question is was this acceptable to any of you, and assuming absolutely not, what area of the code book describes the violation of standard practice, or at least in general, at which point would most of you have done something different or have not done the job at all? The specifics surrounding the installation itself are not what I'm looking for, that I already know what was and wasn't violated, I'm just looking at the standard of practice and ethics side of this, even if not in the code book.
Thanks
I've been tasked with a matter to determine if someone violated any NEC standards or at least standard practice within our field. To keep this simple and brief, an electrician was called for a furnace not working. It was determined the wiring in the conduit above the furnace supplying it shorted out due to a crack in the furnace allowing significant heat to escape and attack the conduit above. The wires were pulled out and replaced. Days later, same issue; wires again pulled out and replaced. Third time, within the same week, electrician replaces conduit and wire because wire was welded to the conduit inside. Fourth time the place burns down with witnesses reporting seeing and hearing significant arcing in the area of the conduit above the furnace and then a fire started in that area.
My question is was this acceptable to any of you, and assuming absolutely not, what area of the code book describes the violation of standard practice, or at least in general, at which point would most of you have done something different or have not done the job at all? The specifics surrounding the installation itself are not what I'm looking for, that I already know what was and wasn't violated, I'm just looking at the standard of practice and ethics side of this, even if not in the code book.
Thanks