JMC01
Member
- Location
- work mostly
I am the production equipment electrical contractor. Part of my scope of work as instructed by the equipment manufacturers is to bond back to building steel. The problem is the building electrical contractor did not install a grounding electrode system as described by the NEC nor did he do any bonding other than a ground rod driven at the main service. There is also a 75 KVA transformer that he installed but refuse to bond the XO tap to building steel. Several electrodes as described by the code are existing but are not bonded together. It is my opinion that this will result in voltage rises if a fault condition occurs and if the electronics are taken out due to that, will it be my responsibility to pay for repair costs?