Good morning,
I need some advise on how to chose the right amount of substructures for parallel UG MV (34.5kV) circuits.
I have 5 3-phase circuits that run parallel to each other with an 8' separation between them. That is, each circuit runs in its own separate trench.
My question is the following, When they reach a point where they have to enter a substructure (Manhole or Vault), can tey merge into one or must they have their own separate structure along the entire way (2.5 miles)?
All 5 are going to the same substation from a solar farm and at no point do they branch out.
I need some advise on how to chose the right amount of substructures for parallel UG MV (34.5kV) circuits.
I have 5 3-phase circuits that run parallel to each other with an 8' separation between them. That is, each circuit runs in its own separate trench.
My question is the following, When they reach a point where they have to enter a substructure (Manhole or Vault), can tey merge into one or must they have their own separate structure along the entire way (2.5 miles)?
All 5 are going to the same substation from a solar farm and at no point do they branch out.