The metering system is subject to the utility's requirements. In my experience they will often want the metering hot sequenced if there are 6 or less disconnects. I am Not sure about the level of detail intended on the drawings: for sure there will need to be a CT cabinet at those current levels, perhaps that is just just assumed on the drawings?