We recently installed a 100A 120/240V 1phase MLO
load center at an out building located approximately 100' from the main house. We used
(3)#2 & (1)#4 ALU direct burial (XHHW.
The load center was for general wiring for the building. From this load center we fed a panel for the swimming pool. We fed the pool panel with conduit 1" with (2)#6 & (2)#8 from a 60A DP breaker.
The local inspector turned it down. He cited 680.25 and said the feeder to the sub panel had to be in conduit as well because it fed the pool panel. Have I misinterpreted the code?
load center at an out building located approximately 100' from the main house. We used
(3)#2 & (1)#4 ALU direct burial (XHHW.
The load center was for general wiring for the building. From this load center we fed a panel for the swimming pool. We fed the pool panel with conduit 1" with (2)#6 & (2)#8 from a 60A DP breaker.
The local inspector turned it down. He cited 680.25 and said the feeder to the sub panel had to be in conduit as well because it fed the pool panel. Have I misinterpreted the code?